CSLB Contractor's Law & Business Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the CSLB Contractor's Law and Business Exam. Use flashcards and multiple choice questions, each with hints and explanations. Enhance your exam readiness!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What does a subcontractor do when they sign a waiver and release form on a public works project?

  1. Gives up the right to sue

  2. Waives their payment rights

  3. Gives up the right to lien the construction funds

  4. Acknowledges completion of their work

The correct answer is: Gives up the right to lien the construction funds

When a subcontractor signs a waiver and release form on a public works project, they are primarily giving up their right to file a mechanics lien against the construction funds. This waiver is a critical part of the process in public projects, which often require ensure that all parties have been paid and that there are no outstanding claims. The purpose of this waiver is to protect the project's owner or general contractor from the possibility of liens being placed against the property for unpaid work. Signing this form indicates that the subcontractor acknowledges they have received payment up to that point or that they cannot assert a claim against the construction funds for additional payment. This is especially relevant in the context of public works, where project owners need to maintain clear title and avoid disruptions from potential liens, which could arise from unpaid subcontractors or suppliers. Other options pertain to different rights or acknowledgments but don't directly address the specific privilege relinquished by the waiver and release in this context. For instance, while a subcontractor may give up the right to sue or waive certain payment rights in other agreements, a waiver and release form specifically relates to the right to lien the project for payment.