What action should a contractor take upon discovering a discrepancy in a set of plans?

  1. Make the correction themselves

  2. Consult with the architect or building designer

  3. Ignore it if it seems minor

  4. Proceed with the job as planned

The correct answer is: Consult with the architect or building designer

When a contractor discovers a discrepancy in a set of plans, the appropriate action is to consult with the architect or building designer. This step is crucial because plans are typically created by professionals who understand the design intent and technical requirements involved in the project. By clarifying the discrepancy directly with the architect or designer, the contractor can ensure that any changes made are aligned with the overall vision and compliance with building codes and regulations. Engaging with the architect or designer facilitates communication, fosters collaboration, and helps to avoid potential issues that could arise from making unauthorized modifications. This collaboration is essential not only for maintaining the project's integrity but also for protecting the contractor from liability that could result from errors or omissions made without proper guidance. Other choices may seem appealing in certain scenarios but can lead to significant problems. Making corrections independently could result in unapproved changes that conflict with the original design, potentially leading to safety concerns or non-compliance with regulatory standards. Ignoring a discrepancy, especially if deemed minor, can deteriorate the quality of the work and create bigger issues later in the project. Lastly, proceeding with the job as planned without addressing the discrepancy could result in construction errors, project delays, and increased costs, which could severely impact the contractor's reputation and future work.