Under what condition can a contractor's dispute be transferred to Superior Court?

  1. If it is under $25,000

  2. If it is a dispute over $50,000

  3. If it is a dispute over $25,000

  4. If the contractor requests it

The correct answer is: If it is a dispute over $25,000

A contractor's dispute can be transferred to Superior Court if the amount in controversy exceeds $25,000. This threshold is significant because it distinguishes between small claims that are typically handled in lower courts and larger disputes that warrant the resources and procedures available in Superior Court. Disputes of this magnitude often involve more complex legal issues, larger monetary claims, or significant damages, necessitating the higher level of judicial scrutiny and procedural formalities characteristic of the Superior Court system. The law emphasizes the importance of allowing parties involved in substantial disputes to have access to the broader remedies and appeals available in higher courts. Smaller claims, those under $25,000, would generally be resolved in small claims court, which is designed to be a simpler, more expedited process. The option regarding a contractor's request for transfer is not sufficient on its own; the determination is primarily based on the dollar amount at stake. This creates a clear distinction in proceedings based on the financial implications of the dispute, emphasizing the court system's structure designed to address varying levels of complexity and monetary value in construction-related conflicts.