In a home improvement contract, which document is typically delivered first?

  1. Three-day notice of right to cancel

  2. 20-Day preliminary notice

  3. The contract

  4. "Notice to Owner"

The correct answer is: "Notice to Owner"

In the context of home improvement contracts, the "Notice to Owner" is typically the first document delivered. This notice serves as a communication tool to inform the property owner about the forthcoming work and to establish that contractors and subcontractors will be involved in the project. It is important for ensuring that the owner is aware of who is working on their property and that they may have certain responsibilities or rights, such as understanding their options for payment and the mechanics lien laws. Delivering this notice prior to the actual contract is essential, as it lays the groundwork for the contractual relationship and informs the owner about potential risks. It is crucial for protecting the contractor’s right to file a lien later if they are not compensated. The other documents mentioned, such as the three-day notice of right to cancel and the 20-Day preliminary notice, are relevant but serve specific purposes in the timeline of a project. The three-day notice applies post-contract signing, informing homeowners of their right to cancel within a certain period, while the 20-Day preliminary notice relates more to the notification of intent to claim a lien and generally comes after the contract is executed.